PROGRESS UPDATE 4,000 SQFT LAYOUT

(NEW PHOTO'S POSTED (Dec 23).

The TMB Model train club is located in Farmingdale on Long Island NY. I started this thread a while back on the 3-rail section but now have some updates. I will be posting updates of our progress. After a voting process where three layouts were proposed what you see below is the clubs selection. The area in the lower right depicts the lower level and contain mostly hidden storage/staging tracks.

The orange and Green lines are the Branch Lines two simple loops for operators, Approx 300 foot run. The Blue and Black lines are based on a simple concept of a dog-bone with a circle wrapped around it, then stretched and twisted throughout the train room. These line when operated conventionally will accommodate two operators for some fun operation, and they are approx 650 feet long

 

Not shown in the diagram and slated for the near future will be a logging line and a ceiling line encircling the entire train room. I hope you enjoy this thread and I will continue to update as time goes by

Steve

 

TMB New Layout

DSC02678

DSC02680

DSC02857

DSC02858

DSC02859

DSC02869

 

Attachments

Photos (8)
Original Post
Originally Posted by L.I.TRAIN:

Not shown in the diagram and slated for the near future will be a logging line and a ceiling line encircling the entire train room.

 

Given the size of the layout room, are there any plans to have the ceiling line connected to the main layout?

 

While I imagine such a thing would not be accessed frequently, but it might be invaluable to be able to swap trains on such a loop without having to physically carry them up to and down from it.

 

I'm assuming that vertical clearances are planned to accommodate modern equipment such as double-stacks. I know the NJ Hirailers have places where unmodified stacks cannot go, although I think that's due to parts of their overall setup containing pre-existing layouts than any design flaws.

 

---PCJ

My YouTube videos

"Wait... Why am I rolling? Am I moving or are the trees moving? What'd you say about my brakes? Youtookoutmywhaaat?

Holy Cow I Can't Staaahp!!"

--MAD's Thomas the "Unstoppable" Tank engine

IN THE SIX WEEK SINCE THE FIRST POSTING,  THE BENCH WORK IN NOW 70% COMPLETED WITH THE TRACK CREW RIGHT BEHIND, IN THIS FIRST PHOTO THE TWO TRACKS CLOSEST TO YOU WILL BE SEEN AND THE FIVE TRACK YARD WILL BE HIDDEN STORAGE, COVERED BY FIVE TRACKS THAT WILL BE PLACED 14" ABOVE. AMAZING PROGRESS AND A TON OF MAN HOURS BY THE MEMBERSHIP.

TMB LAYOUT PROGRESS 004

TMB LAYOUT PROGRESS 005

TMB LAYOUT PROGRESS 006

TMB LAYOUT PROGRESS 007

TMB LAYOUT PROGRESS 008

TMB LAYOUT PROGRESS 009

TMB LAYOUT PROGRESS 011

Attachments

Photos (7)

WOW The TMB bench work and track is really coming along. I am looking forwaed to seeing trains running on this new layout. You guys are going to have a GREAT looking RR to run. Thanks for sharing with us.

Running CN, GTW & Santa Fe Power...Reg April 09,2006

 

 

That look's like a nice start on the layout it take's a lot of work to do a layout that big, I have 1'000 sq.ft. room for my layout I wish I had 1'700 sq.ft. any bigger than that it get to hard for one person to run, I need the space for yard's and building's .

 

Guy   

         

Gee I did not realise that the TMB new layout was 4,000 sq ft. Geeeee that is really BIGGGGGGGGG. Congratulations guy's for taking on such a large project.....Please keep the pictures coming our way.

Merry Christnas.

Running CN, GTW & Santa Fe Power...Reg April 09,2006

 

 

Pops

Appreciate your following this thread. Its a lot easier to build something this BIG in a club with 70 members. Also since our last build we have a fair number of the members now retired so they have more available time. Last we were able to salvage a lot of the material from the previous layout, building wood and some track etc. so supplies were readily available.

THANKS

Steve