Bench work Construction complete!
Well back at it again, I have made some more progress completing the bench work construction. The entire layout is now covered with Homasote. I have placed this down as the base on top of the OSB. It is also on the elevated sections at the back of the layout. The grade to and from these elevated areas will be a combination of a trestle extension (I will extend the trestle at the back left of the layout to make a curve to meet he back elevated area) the inside track will ramp up using foam. The same type of approach will be on the back right corner where it comes back down.

The homosote is painted with a flat latex paint, a kind of “sandy – mud - dirt color” I didn’t do this before, and when I saw the results others had here on the forum I tried it out.

After the homasote was installed and painted, I added wood trim boards around the layouts – 1x6 dimensional lumber and then painted flat black to match the existing construction.

View from the bottom of the stairs 
IMG_2163
Harbor area in the foreground right, look back across the city to the left. The harbor will have 2” foam to elevate the pier, I plan to install that next. I have removed some of the supports from the elevated line on the city peninsula, I am reworking that to have a line run beneath it, and then two sidings for passenger cars for a large passenger terminal. 
IMG_2164IMG_2165
Harbor in the front left, looking at the smaller town and the “mountain” top “ amusement park on the right.

IMG_2166IMG_2167
I have started to stage track and switch’s amongst other things in the yards and service area

IMG_2168
Yards to the right, the gap you see is so I can get to the breaker panel behind the framed poster. This will have a few removable bridges for easy access.
 
IMG_2169IMG_2170IMG_2171IMG_2172
Looking back at the service area

IMG_2173

 

I stocked up on some conduit clamps to start installing for wire management, and while at it I will re layout my central wiring area to get better access to the AIU terminal strips.

Things always seem to take longer than I expect, but I think the progress is OK. I am looking forward to putting the saws away and working on track and wiring next. As always comments and suggestions welcome.

Attachments

Images (11)
  • IMG_2163
  • IMG_2164
  • IMG_2165
  • IMG_2166
  • IMG_2167
  • IMG_2168
  • IMG_2169
  • IMG_2170
  • IMG_2171
  • IMG_2172
  • IMG_2173
Last edited by Rich883

OGR Publishing, Inc., 1310 Eastside Centre Ct, Suite 6, Mountain Home, AR 72653
800-980-OGRR (6477)
www.ogaugerr.com

×
×
×
×
×