1/28/20 to 2/10/20 – Believe it or not, that was all that really got accomplished in 2019. Looking back, I can’t tell you what else I was busy with, but we all know how life just seems to get in the way of our hobbies sometime. Anyway the next wall was finally insulated and framed.
2/23/20 – Another wall is insulated and framed. I had to install this wall in front of the soil lines, which meant I also had to relocate a cold water line at the ceiling where the top plate needed to go. It all worked out in the end.
3/1/20 – On the last area I had to frame, I had to install a doorway into the furnace room. Time to watch more YouTube videos. I was happy with the way it came out. I also had to frame around a triangle shaped bump out. We have a corner fire place upstairs and this is the foundation for the fireplace. Since this is inside the basement, I did not insulate these walls.