Updated 7/4/2019:

Happy Independence Day everyone!!!!

Today, I focused on construction of the sub-roadbed for the Pennsy Cross-section (eastern approach to the Stone Arch).

In these next two photos, I'm clamping the longitudinal stiffener for the side that will be closest to the viewer when the section is flipped over.

Benchwork_361_Benchwork_362_
This photo hints at how the section will dove-tail with the existing benchwork.
Benchwork_363_



Now I am positioning the other longitudinal stiffener.  You never have too many clamps!

Benchwork_364_

After flipping the section upright, I screwed the sub-roadbed to the longitudinal stiffeners. The vertical board will snuggle up against the Stone Arch.

DSCN6111

DSCN6112

The photo is a little blurry, but you can see that carpenter's shims are our friends!

DSCN6117

Finally, I added a diagonal brace between the 90 degree cross-members. I think we eliminated any chance of roadbed deflection.

DSCN6118

More when I know it.  

George

Attachments

Images (9)
  • Benchwork_361_
  • Benchwork_363_
  • Benchwork_364_
  • Benchwork_362_
  • DSCN6111
  • DSCN6112
  • DSCN6115
  • DSCN6117
  • DSCN6118
Last edited by G3750

OGR Publishing, Inc., 1310 Eastside Centre Ct, Suite 6, Mountain Home, AR 72653
800-980-OGRR (6477)
www.ogaugerr.com

×
×
×
×
×