I'm posting this as a lesson learned for all of you just starting layouts - specifically raised roadbed.

 

I started building my PRR Panhandle Division in late 2005 and completed most of the trackwork in early 2007.  You can see it over on the Photo Forum. 

 

My original thinking was to make the layout portable and lightweight.  I built a number of 3'x5', 2'x4', 4'x6' tables from 1"x4" pine with 2"x2" braced legs.  These provided a very stable and strong framework.  So far, so good.

 

Then I committed a mistake which has plagued operations ever since.  I used plywood that was too thin to adequately support the roadbed. 

 

The lesson is:  Use 5/8" or thicker plywood for your subroadbed!

 

Thinner plywood tends to sag.  My subroadbed is raised or cookie-cutter and supported by risers with cleats.  Thinner plywood subroadbed requires many more supports or risers.  My Williams steamers are very forgiving and tend to have adequate pilot (cow-catcher) clearances, but other locomotives do not and tend to rub the track and short out.  One of the benefits of inviting friends to bring and run their engines has been to identify areas that are troublesome.

 

Over the years, I've had to fix a number of low spots or sagging track joints.  Having to reinforce these is a pain, but much less painful than replacing the subroadbed altogether.  My roadbed supports are spaced about 16-20" apart and that's just too wide.  So I am having to add additional bracing.

 

Anyway, I thought this might be a good way to keep someone from making the mistakes I made.

 

Please check out the PRR Panhandle on the Photo Forum and leave a comment.  I'd love to hear from you!

 

George

 

Original Post

Replies sorted oldest to newest

I found sagging cookie cutter subbed can be supported by horizontal 1"x3" or 1"x4" beams below it between the risers. Of course, it requires access from below and the beams need to be true as well. I found it to work well when I screwed them in place from above, forming something like a "T". Shorter pieces were required to follow curves. But they easilly will span a 16"-20" gap.

In my experience it is not the thickness but the design of the subroadbed.

 

5.2mm (nominal 1/4") Laun can be used if you adequately support it. 

 

Consider using a spline variation: 

 

For a single track 0 gauge cookie cutter raised road bed, mount 1 x 4 risers up to the exact  needed height.  Then run 1 1/2" wide slit strips of the same laun on a vertical plane fastened parallel along the top of the risers on each side for the subroad bed support.   Use spacer tie in pieces of 1 x 4 X 1 1/2 as spline support/spline gauge blocks between risers.  Do not have more than 12"-16" of run without a riser or spacer block.  Predrill wire management holes in all 1 x 4 risers and spacer tie in pieces

 

Place rough trimmed 8' long panels of laun on the top of the laun rails and pencil trace up from the bottom sliding lengthwise against a 1/2" spacer off the vertical lattice so as to arrive at a 5" wide subroadbed. 

 

Flip the penciled panel over and carefully cut out that one panel and smoothly sand the edges.  Repeat this over and over around the layout.  Carefully position all joints between risers so as to provide space for the bottom splice plates .

 

Note, mock up each and every laun subroadbed joint so as to fasten each bottom splice plate on ONE END with Tightbond III

 

Run a bead of premium urathan construction adhesive along the top edge of all the 1 1/2"  lattice strips.  Then carefully place all the pre cut, pre joined subroad bed on the adhesive and let dry over night.  A brad gun comes in handy here.  Light duty clamps can also assist.

 

You will have an 10 minute or so open window for position adjustments.  Just make sure you have well spread out flat weighted surfaces holding everything in place while drying.  Better to use more adhesive than too little.

 

You will screw up somewhere, you will miss some spots, you will push some adhesive off the top edge.  That's OK.  Just use enough to allow for a safety margin.

 

Remember, urathane cinstruction just has to touch both surfaces up to 3/8" apart.  Tightbond III like all wood glues needs to be clamped together for a minimum of 30 minutes.  Actual spec is 175 lbs per sq. inch clamping pressure.

 

In less than an hour take a thin piece of cardboard, like a business card, then fold it in half and plow it lightly along the glued crevice to scoop up excess nasty looking glue. Make it pretty. 

 

Use gloves.  Clean spilled adhesive immediately off skin with mineral spirits soaked rag then wash hands with soap and water.  Do this right away with each glue/skin contact.

 

Practice subroadbed assembly with some scrap pieces.  This will become one of the strongest structual components of any layout.  Typically I would use either cork or Homobed roadbed on top.  Always make the subroad bed wider than you might think.  This will help to attach any scenery terrain material.  You could get away with occasional 32" straight spans using this method.  Try to keep most risers at 16".

 

If you feel uncertain with the glue you can screw it or shoot it with 1/4" crown X 1" long  staples.  IMO, glue is best.  Do not screw into end grain.

 

 

There are several other ways to develope strong subroad bed.

 

Perhaps the easiest way is to simply use a 7 ply minimum 3/4" (23/32") Birch/Maple shop grade plywood.  Shop grade has a finish that is not furniture stain grade but does have the same strength qualities.  

 

Going to a quality 3/4" thickness panel IME, is the big step.  3/4" seems to provide  the strong construction margin the average D.I.Y. needs.

 

Avoid buncha pieces.  Never piece at the very top or very bottom of a grade. 

 

There is no one right way to build good benchwork. 

 

Just run away from the "That'll do" or the "That's good enough" crowd.

 

Cheating on your layout is like cheating on your spouse, it will catch up to you in one way or another. tt

 

www.curvedbenchwork.net

Last edited by Tom Tee
Post
The Track Planning and Layout Design Forum is sponsored by

AN OGR FORUM CHARTER SPONSOR

OGR Publishing, Inc., 1310 Eastside Centre Ct, Suite 6, Mountain Home, AR 72653
800-980-OGRR (6477)
www.ogaugerr.com

×
×
×
×
Link copied to your clipboard.
×
×